County of Hawaii
Planning and Permitting Demonstration
April 19, 2016
Title Text
Introductions
Hawaii Information Consortium
eHawaii.gov
Key Project Team Members
i2 - Permits to Install
User registration
HIOSH Supervisor module
HIOSH Inspector module
Elevator Company module
Streamlined permit application process
Workflow routing
Application framework development
All encompassing database
Landing Page
Login
HIOSH Supervisor
Dashboard with real time reports
Alerts and notifications
Add/edit/delete inspectors
Supervisor Queue
Manage MyProfile
View Permit Installation application details
Approve/deny applications
Assign application to an inspector
View the application history
Dashboard
Other real time reports
Other real time reports
Alert Notifications Panel
Alerts
Supervisor Queue
Approved Items
Manage Inspectors
Add Inspectors
View/Manage MyProfile
View Installation Details
View Installation Details (2)
View History
Approve or Deny requests
Assign to an Inspector
HIOSH Inspector
Dashboard with real time reports
Alerts and notifications
Inspector Queue
Manage MyProfile
View Permit Installation application details
Approve/deny applications
View the application history
Elevator company
Dashboard with real time reports
Alerts and notifications
Submit an application for a Permit to Install
Submit multiple applications
Fill out compliance sheets
Queue
Manage MyProfile
View Permit Installation application details
Pay for applications
View the application history
Installation Form - Location
Review Page
Add Equipment
Add Equipment Owner
Add Installer
Installer Verification
Updated Review Page
Compliance Sheet(s)
Compliance Sheet(s)
i2 - What's next?
Schedule review sessions with HIOSH team
Implement final changes and schedule HIOSH training sessions (2)
Finalize communication plan with elevator community
Begin Iteration 3 (i3) planning sessions
i3 - Inspections
Leverage the existing permit application framework to fast track development on the inspections module
Target start date late February or early March
Target finish date early June
i4 - Alterations
Leverage the existing permit application framework to fast track development on the alterations module
Target start date early July
Target finish date early October
Summary
HIC has been waiting to re-engage with HIOSH team
Iteration 2 (i2) development is complete
Finalize steps for Production deployment
Iteration 3 nearly ready to start
Made with Slides.com