Elevator Installation and Permitting Project



Update January 21, 2015

Title Text

Current status

  • Iteration 2 (Installation permits): Development is complete
  • Ready for HIOSH review and testing
  • Target start - Iteration 3 (Inspections) - Late February

 i2 - Permits to Install

  • User registration
  • HIOSH Supervisor module
  • HIOSH Inspector module
  • Elevator Company module
  • Streamlined permit application process
  • Workflow routing
  • Application framework development
  • All encompassing database

Landing Page

Login

HIOSH Supervisor

  • Dashboard with real time reports
  • Alerts and notifications
  • Add/edit/delete inspectors
  • Supervisor Queue
  • Manage MyProfile
  • View Permit Installation application details
  • Approve/deny applications
  • Assign application to an inspector
  • View the application history

Dashboard

Other real time reports

Other real time reports

Alert Notifications Panel

Alerts

Supervisor Queue

Approved Items

Manage Inspectors

Add Inspectors

View/Manage MyProfile

View Installation Details

View Installation Details (2)

View History

Approve or Deny requests

Assign to an Inspector

HIOSH Inspector

  • Dashboard with real time reports
  • Alerts and notifications
  • Inspector Queue
  • Manage MyProfile
  • View Permit Installation application details
  • Approve/deny applications
  • View the application history

Elevator company

  • Dashboard with real time reports
  • Alerts and notifications
  • Submit an application for a Permit to Install
  • Submit multiple applications
  • Fill out compliance sheets
  • Queue
  • Manage MyProfile
  • View Permit Installation application details
  • Pay for applications
  • View the application history

Installation Form - Location

Review Page

Add Equipment

Add Equipment Owner

Add Installer

Installer Verification

Updated Review Page

Compliance Sheet(s)

Compliance Sheet(s)

 i2 - What's next?

  • Schedule review sessions with HIOSH team
  • Implement final changes and schedule HIOSH training sessions (2)
  • Finalize communication plan with elevator community
  • Begin Iteration 3 (i3) planning sessions

 i3 - Inspections

  • Leverage the existing permit application framework to fast track development on the inspections module
  • Target start date late February or early March
  • Target finish date early June

 i4 - Alterations

  • Leverage the existing permit application framework to fast track development on the alterations module
  • Target start date early July 
  • Target finish date early October

 Summary

  • HIC has been waiting to re-engage with HIOSH team
  • Iteration 2 (i2) development is complete
  • Finalize steps for Production deployment
  • Iteration 3 nearly ready to start