QA Roles and Responsibilities:
QA is a set of “activities focused on providing confidence that quality requirements will
be fulfilled.”
QA Analyst
Understand the Acceptance Criteria
Actively participate in Scrum rituals
Create Test Cases(Regression, Smoke,
Feature, Integration, etc.)
Create QA Jira Tasks and subtasks
Execute Test Cases
File defects and retest
Capture Test Evidence
Follow Mobiquity’s Testing guidelines
QA Lead
Accountable for all QA activities (left and below)
Create Test Plans, seek approvals, execute the Test
Plans
Coordinate the Testing Effort
Test Suites and Work
Assignments
Approve Test Scenarios & Test Cases
Triage Defects
Produce and Socialize Quality Metrics
Provide Test Execution & Summary Reports
Adhere to Timelines
Communicate Project Risks & Blockers
Procure Test Devices
Attend Project Status Calls
Advise on Go
no
go before releases
QA Process
-
Testing Phases
One misconception in software testing is that it is often perceived as just “
Implementation
and Execution
” (write test cases and execute test cases). However, a mature Testing Process
starts with the appropriate level of Planning.
1.
Start
Project initiation Activities
Resource alignment
Access and tools setup
●
Jira
●
qTest
●
Project Wiki page
●
Test devices/equipment
●
Requirements specification document
●
Visual design document
●
Others
Summary
: Provide a
-
one
-
line summation of the actual
incident so others can understand what the incident is and
how it was discovered.
Description:
Provide thorough details on the incident. Include
any information that is not already included in the defect
summary. Avoid just copying and pasting the defect
summary in the description. Include additional information
such as:
●
Pre
-
requisites:
List any pre
-
conditions
●
Steps to reproduce:
●
Test Data:
User Credentials, Account Numbers, Roles, etc.
●
Actual result:
What you see
●
Expected result:
What you expect to see based on the
acceptance criteria
●
Test Case:
List the Test Case(s) affected by this issue
Defect
Documentation
How a defect is documented is crucial to the project.
Environment
: Provide details related to the test
environment, platform (iOS, Android, Web, Server,
etc.), build number, Operating Systems and
versions, Browsers and versions, Database version,
Device information, etc.
Attachments
: A defect must have at least one
attachment. For example: Logs, Gifs, Videos,
Screenshots, Charles Proxy sessions, cURL, etc.
Severity:
The impact a defect has on the
functionality of the application.
●
S1
-
ShowStopper
●
S2
-
Severe
●
S3
-
High
●
S4
-
Medium
●
S5
-
Low
25
25 / 30
Before
●
UAT Test Plan is up to date and approved
●
UAT Entry Criteria is met and known
issues have been communicated
●
UAT Kickoff meeting with the Client to set
expectations
●
Smoke Test cases and Test Suites are set
●
Business users are aware on how to
execute test cases and log defects
●
‘Customer Bug’ Type is used to log
customer reported defects
UAT
During
●
Run Smoke tests on every new UAT build
generated
●
QA Lead to attend daily defect triage call
●
Ensure any defect filed by the Client is indeed
a defect and not enhancement/change
requirement
●
Agree on a Severity and a Priority. Not every
Customer Bug is a P1 or S1.
●
Reproduce every defect filed
●
Retest the defect and impacted regression
after a defect is fixed
●
Share Daily Test Execution Report
After
●
QA Lead to calculate Defect Escape
Ratio (DER)
●
Share RCA Report if DER is above
Quality Goal (20%)
●
Creates UAT Summary Report
User Acceptance Testing