Towards Phase II
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
| Location | # Switches |
|---|---|
| USA15 | 3 |
| US15 | 0 |
| SDX1 | 0 |
| UX15 | 0 |
Count of switches in primary locations
The number of switches assigned is based on the HGTD network requirements gathered.
Switches for FELIX are not included here and are included in TDAQ counting only.
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
The switches are not in ACES.
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
Summary of Activities for HGTD
| Activity | Starting | Ending |
|---|---|---|
| Deployment of new network switches for HGTD, ITK, TC and ZDC (USA15 level 1) | 25/May/27 | 05/31/2027 |
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
JIRA ticket for Offline Discussion
There is a JIRA ticket created for discussion. The tickets is named:
| Consolidate the network distribution of the HGTD switches |
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
Routers Phase II
100G 4/8
10G 268/320
1G 0/80
The router's maintenance period is not yet scheduled. It's expected to happen in the shadow of the DSS upgrade. The duration will depend on the final chassis selected, ranging from 2 to 5 days.
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
How to use the planning page?
1. Select the subsystem that you are intereseted
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
How to use the planning page?
2. Select the interested building
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
How to use the planning page?
3. Use the flow diagram in the right side to see the stages of the network in different dates.
On each date, new elements are marked with a yellow star, removal with a red mark and upgraded elements with a green arrow.
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe
How to use the planning page?
4. Hover the mouse over the elements to see subsystems or comments.
HGTD Coordination Meeting - 10.04.2024 - Gustavo Uribe