Towards Phase II
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe
Disclaimer: All dates provided are subject to changes in the LHC schedule.
Location | Phase II |
---|---|
USA15 - Muon | 4 |
USA15 - NSW | 2 + 1? |
SDX1 | 0 |
US15 - NSW | 4 |
SGX1 | 1 |
Count of switches in primary locations
The number of switches assigned is based on the Muon network requirements gathered.
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe
Switches for FELIX, TGC-SL, MDT-TP and RPC-SL are not included here and are included in TDAQ counting only.
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe
Summary of Activities for LAR
Activity | Starting | Ending |
---|---|---|
Deployment of switches in Y.27-05.A1 and Y.30-05.A1 | 13/08/2026 | 19/08/2026 |
Deployment of switches in Y.2[7-9]-05.A2 | 04/01/2027 | 08/01/2027 |
Rolling replacement of switches in Y.18-16.A2, Y.31-19.A2 and Y.29-02.A2. | 04/01/2027 | 15/01/2027 |
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe
Routers Phase II
100G 4/8
10G 268/320
1G 0/80
The router's maintenance period is scheduled for the first quarter of 2026. The duration will depend on the final chassis selected, ranging from 2 to 5 days.
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe
How to use the planning page?
1. Select the subsystem that you are intereseted
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe
How to use the planning page?
2. Select the interested building
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe
How to use the planning page?
3. Use the flow diagram in the right side to see the stages of the network in different dates.
On each date, new elements are marked with a yellow star, removal with a red mark and upgraded elements with a green arrow.
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe
How to use the planning page?
4. Hover the mouse over the elements to see subsystems or comments.
TC-Muon Coordination Meeting - 20.09.2024 - Gustavo Uribe