Shipbuilding OpenPLM
NSRP RA 21 Project Proposal
Prime:
SSI USA
Team:
GD BIW
Austal USA
VTHM
Nichols Bros.
Auros
Duration:
24 Months
This proposal offers a staged approach to a shipbuilding OpenPLM implementation where project participants will evaluate technology and processes for integration with a 3D design tool. This initiative proposes an integrated PLM solution including requirements checking and knowledge provisioning.
| Program Funds | $1.65M |
| Cost Share | $1.65M |
| Total | $3.3M |
Change Cost Management
NSRP RA 21 Project Proposal
Prime:
Austal USA
Team:
GD BIW
CostFact GmBH
NWE LLC.
SSI USA
Duration:
24 Months
Integrate the 3D design model with cost analysis software (CostFact) to compare impact/value of model design changes based on detailed historical cost data. Provide faster optimizations for cost efficient designs and shorten review time to support earlier changes to minimize disruption or rework.
| Program Funds | $860K |
| Cost Share | $1.6M |
| Total | $2.4M |
VTHM
Initial Build Strategy & Yard Capacity Planning
NSRP RA 21 Project Proposal
Prime:
Marinette Marine (FMM)
Team:
GD BIW
ProModel Corp.
VTHM
SSI USA
Duration:
24 Months
Develop an integrated, yard-wide scheduling simulation tool supporting instantaneous area and shop analysis for the entire facility, individual shops, and assembly areas. Enable advanced multi-build strategy simulation for comparison based on facility and schedule constraints.
| Program Funds | $2M |
| Cost Share | $2M |
| Total | $4M |
Ship Repair & Compartment Closeout
NSRP RA 21 Project Proposal
Prime:
Marinette Marine (FMM)
Team:
GD BIW
ProModel Corp.
VTHM
SSI USA
Duration:
24 Months
Ship repair and compartment closeout planning.
| Program Funds | $2M |
| Cost Share | $2M |
| Total | $4M |
Open Common Parts Catalog
NSRP RA 21 Project Proposal
Prime:
Conrad Shipyards
Team:
GD BIW
FMM
VTHM
SSI USA
Duration:
24 Months
Create, implement and document an open-source Common Parts Catalog (CPC) utilizing modern web technologies and leveraging previous CPC project work and definitions.
| Program Funds | $1M |
| Cost Share | $1M |
| Total | $2M |
Digital Scan Management
NSRP RA 21 Project Proposal
Prime:
Austal USA
Team:
GD BIW
D'Angelo Tech
VTHM
SSI USA
Duration:
24 Months
Provide a solution to storing and maintaining large digital scan data sets, including possible integration to other business processes.
| Program Funds | $500K |
| Cost Share | $500K |
| Total | $1M |
DotProduct
VizSeek Visual Search Integration
NSRP RA 21 Project Proposal
Prime:
HII
Team:
GD BIW
Imaginestics LLC
VTHM
SSI USA
Duration:
24 Months
Drastically increase search utility by allowing users to search based on a visual representation of part objects to reduce time and decrease incidents of sourcing parts from different suppliers if not needed.
| Program Funds | $750K |
| Cost Share | $750K |
| Total | $1.5M |
FMM
Build to Test
NSRP RA 21 Project Proposal
Prime:
HII
Team:
GD BIW
VTHM
SSI USA
Duration:
24 Months
Create a drawing/referenced output with test points within a system.
| Program Funds | $750K |
| Cost Share | $750K |
| Total | $1.5M |
FMM
Robotic Pipe/HVAC Fabrication &Welding
NSRP RA 21 Project Proposal
Prime:
Austal USA
Team:
GD BIW
VTHM
SSI USA
Duration:
24 Months
Leverage design model weld data to derive a low-cost, proof-of-concept robotic welding plan for pipe spools and complex HVAC transitions.
| Program Funds | $1.6M |
| Cost Share | $1.6M |
| Total | $3.2M |
FMM
Navus Automation
Shipyard Analytics
NSRP RA 21 Project Proposal
Prime:
LMI (Ben Kassel)
Team:
GD BIW
VTHM
SSI USA
Duration:
24 Months
Provide advanced data analytics tools to enhance business insights leveraging Big Data approaches.
| Program Funds | $1M |
| Cost Share | $1M |
| Total | $2M |
FMM
ShipSpace AR (Design/Review)
NSRP RA 21 Project Proposal
Prime:
Austal USA
Team:
GD BIW
VTHM
SSI USA
Duration:
24 Months
Integrate the Virtual Reality Software “ShipSpace” with the 3D ShipConstructor Product Model. Providing a personal perspective on a collaborative design model review where communications is instantaneous benefiting real-time decision making.
| Program Funds | $2M |
| Cost Share | $2M |
| Total | $4M |
FMM
D’Angelo Tech
ABS