ATCN Planning for LAR
Towards Phase II
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
Disclaimer: All dates provided are subject to changes in the LHC schedule.
Location | Phase II |
---|---|
USA15 - LASP + DT | 15 |
USA15 - Other LAR | 2 |
SDX1 - TDAQ Sysadmins | 0 |
US15 | 0 |
Count of switches in primary locations
The number of switches assigned is based on the LAR network requirements gathered.
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
The switches were already located in ACES for example.
However, they were removed by mistake in:
Y.27-05.A1
Y.30-05.A1
Y.27-05.A2
Y.28-05.A2
Y.29-05.A2
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
Summary of Activities for LAR
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
Activity | Starting | Ending |
---|---|---|
Deployment of switches in Y.27-05.A1 and Y.30-05.A1 | 13/08/2026 | 19/08/2026 |
Deployment of switches in Y.2[7-9]-05.A2 | 04/01/2027 | 08/01/2027 |
Rolling replacement of switches in Y.18-16.A2, Y.31-19.A2 and Y.29-02.A2. | 04/01/2027 | 15/01/2027 |
Routers Phase II
100G 4/8
10G 268/320
1G 0/80
The router's maintenance period is scheduled for the first quarter of 2026. The duration will depend on the final chassis selected, ranging from 2 to 5 days.
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
Thanks!
How to use the planning page?
1. Select the subsystem that you are intereseted
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
How to use the planning page?
2. Select the interested building
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
How to use the planning page?
3. Use the flow diagram in the right side to see the stages of the network in different dates.
On each date, new elements are marked with a yellow star, removal with a red mark and upgraded elements with a green arrow.
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
How to use the planning page?
4. Hover the mouse over the elements to see subsystems or comments.
TC-Lar Coordination Meeting - 16.09.2024 - Gustavo Uribe
ATCN Planning for LAR
By Gustavo Andrés Uribe Gómez
ATCN Planning for LAR
- 3