-- Some information based on the data in the system
- The data is until 2013-02-20. For further data, we will have a report page which will be updated automatically.
- Only the issues in active project are included.


- Lifecycle = Issue Closed Time - Issue Created Time
- Only Closed issues are included here.
- If an issue has been closed and reopened several times, the last closed time is counted here.
- Why the value for DL is above average so much?

- One Epic could contains several stories, and the stories may be included in different sprint, so the value for Epic is above the average a lot.
Percentage of issue lifecycle in timeslots


- Issue Get Estimated = When the issue has the estimation - Issue created time
- All the issues here are the one have estimations, if a issue doesn't have estimation at all, it is not included.


- Issue get Story Points = Story Points added to issue - Issue Created


-
Issue Being GLed on UAT = Issue UAT GLed - Issue Created


- Development Lifecycle = UAT GLed - Sprint Start
- Only the issues which have been added into Sprint are counted here.
- If an issue is added into several sprints. The first sprint start time is picked here.
- SD & SUX?


- Waiting before get into production = Sprint Start - Issue Created
- Only the issue was added into at least one sprint are counted here.