PROJECT INFORMATION

Shipbuilding OpenPLM

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

SSI USA

Team:

GD BIW

Austal USA

VTHM

Nichols Bros.

Auros

Duration:

24 Months

Deliverables/Benefits/ROI

  • Implement a Digital Tapestry with full traceability of configuration managed product structure throughout the product.
  • Realize a Digital Twin as a direct representation of a specific revision of product data for a vessel. This provides a significant asset for competitive bidding on post ship delivery service contracts.

This proposal offers a staged approach to a shipbuilding OpenPLM implementation where project participants will evaluate technology and processes for integration with a 3D design tool.  This initiative proposes an integrated PLM solution including requirements checking and knowledge provisioning.

Financial (ROM Estimate)

Program Funds $1.65M
Cost Share $1.65M
Total $3.3M

PROJECT INFORMATION

Change Cost Management

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

Austal USA

Team:

GD BIW

CostFact GmBH

NWE LLC.

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • Instant cost analysis/management based on historical data.
  • Optimization of cost variables from 3D design models.
  • Accurate and early cost estimate/planning to minimize impact of changes.

 

Integrate the 3D design model with cost analysis software (CostFact) to compare impact/value of model design changes based on detailed historical cost data. Provide faster optimizations for cost efficient designs and shorten review time to support earlier changes to minimize disruption or rework.

Financial (ROM Estimate)

Program Funds $860K
Cost Share $1.6M
Total $2.4M

VTHM

PROJECT INFORMATION

Initial Build Strategy & Yard Capacity Planning

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

Marinette Marine (FMM)

Team:

GD BIW

ProModel Corp.

VTHM

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • Deliver comparative analysis on multi-build strategy scenarios to maximize facility efficiencies and plan for new projects to fit into current yard-wide production cycles.

 

Develop an integrated, yard-wide scheduling simulation tool supporting instantaneous area and shop analysis for the entire facility, individual shops, and assembly areas.  Enable advanced multi-build strategy simulation for comparison based on facility and schedule constraints.

Financial (ROM Estimate)

Program Funds $2M
Cost Share $2M
Total $4M

PROJECT INFORMATION

Ship Repair & Compartment Closeout

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

Marinette Marine (FMM)

Team:

GD BIW

ProModel Corp.

VTHM

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • Deliver comparative analysis on multi-build strategy scenarios to maximize facility efficiencies and plan for new projects to fit into current yard-wide production cycles.

 

Ship repair and compartment closeout planning.

Financial (ROM Estimate)

Program Funds $2M
Cost Share $2M
Total $4M

PROJECT INFORMATION

Open Common Parts Catalog

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

Conrad Shipyards

Team:

GD BIW

FMM

VTHM

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • Deliver fully functional Parts Catalog based on the CPC
  • Free/Open Source Software
  • Documentation and instructions for any shipyard to implement results

 

Create, implement and document an open-source Common Parts Catalog (CPC) utilizing modern web technologies and leveraging previous CPC project work and definitions.

Financial (ROM Estimate)

Program Funds $1M
Cost Share $1M
Total $2M

PROJECT INFORMATION

Digital Scan Management

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

Austal USA

Team:

GD BIW

D'Angelo Tech

VTHM

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • Digital scan repository and management system
  • Integrated data environment

Provide a solution to storing and maintaining large digital scan data sets, including possible integration to other business processes.

Financial (ROM Estimate)

Program Funds $500K
Cost Share $500K
Total $1M

DotProduct

PROJECT INFORMATION

VizSeek Visual Search Integration

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

HII

Team:

GD BIW

Imaginestics LLC

VTHM

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • 200 workstations @5% time savings
    • $500k/year saved
  • 10 purchasing $5M annual saving 2%
    • $100k/year saved

Drastically increase search utility by allowing users to search based on a visual representation of part objects to reduce time and decrease incidents of sourcing parts from different suppliers if not needed.

Financial (ROM Estimate)

Program Funds $750K
Cost Share $750K
Total $1.5M

FMM

PROJECT INFORMATION

Build to Test

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

HII

Team:

GD BIW

VTHM

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • Testing integrations for build  

Create a drawing/referenced output with test points within a system.

Financial (ROM Estimate)

Program Funds $750K
Cost Share $750K
Total $1.5M

FMM

PROJECT INFORMATION

Robotic Pipe/HVAC Fabrication &Welding

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

Austal USA

Team:

GD BIW

VTHM

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • Provide integration for robotic pipe/HVAC welding from the design model.
  • Address highest success rate pipe spools.
  • Provide drop-in, turnkey solution

 

Leverage design model weld data to derive a low-cost, proof-of-concept robotic welding plan for pipe spools and complex HVAC transitions.

Financial (ROM Estimate)

Program Funds $1.6M
Cost Share $1.6M
Total $3.2M

FMM

Navus Automation

PROJECT INFORMATION

Shipyard Analytics

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

LMI (Ben Kassel)

Team:

GD BIW

VTHM

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • Big Data Analytics for shipyards
  • Business Decision Dashboards

Provide advanced data analytics tools to enhance business insights leveraging Big Data approaches.

Financial (ROM Estimate)

Program Funds $1M
Cost Share $1M
Total $2M

FMM

PROJECT INFORMATION

ShipSpace AR (Design/Review)

NSRP RA 21 Project Proposal

OBJECTIVE

Prime:

Austal USA

Team:

GD BIW

VTHM

SSI USA

Duration:

24 Months

Deliverables/Benefits/ROI

  • Reduces model review cycle time by having stakeholders “inside” the 3D virtual model with the ability to navigate the model independently from others also inside,  a life like experience.

Integrate the Virtual Reality Software “ShipSpace” with the 3D ShipConstructor Product Model.  Providing a personal perspective on a collaborative design model review where communications is instantaneous benefiting real-time decision making. 

Financial (ROM Estimate)

Program Funds $2M
Cost Share $2M
Total $4M

FMM