HIOSH
Elevator Installation and Permitting Project
Update January 21, 2015
Title Text
Current status
- Iteration 2 (Installation permits): Development is complete
- Ready for HIOSH review and testing
- Target start - Iteration 3 (Inspections) - Late February
i2 - Permits to Install
- User registration
- HIOSH Supervisor module
- HIOSH Inspector module
- Elevator Company module
- Streamlined permit application process
- Workflow routing
- Application framework development
- All encompassing database
Landing Page
Login
HIOSH Supervisor
- Dashboard with real time reports
- Alerts and notifications
- Add/edit/delete inspectors
- Supervisor Queue
- Manage MyProfile
- View Permit Installation application details
- Approve/deny applications
- Assign application to an inspector
- View the application history
Dashboard
Other real time reports
Other real time reports
Alert Notifications Panel
Alerts
Supervisor Queue
Approved Items
Manage Inspectors
Add Inspectors
View/Manage MyProfile
View Installation Details
View Installation Details (2)
View History
Approve or Deny requests
Assign to an Inspector
HIOSH Inspector
- Dashboard with real time reports
- Alerts and notifications
- Inspector Queue
- Manage MyProfile
- View Permit Installation application details
- Approve/deny applications
- View the application history
Elevator company
- Dashboard with real time reports
- Alerts and notifications
- Submit an application for a Permit to Install
- Submit multiple applications
- Fill out compliance sheets
- Queue
- Manage MyProfile
- View Permit Installation application details
- Pay for applications
- View the application history
Installation Form - Location
Review Page
Add Equipment
Add Equipment Owner
Add Installer
Installer Verification
Updated Review Page
Compliance Sheet(s)
Compliance Sheet(s)
i2 - What's next?
- Schedule review sessions with HIOSH team
- Implement final changes and schedule HIOSH training sessions (2)
- Finalize communication plan with elevator community
- Begin Iteration 3 (i3) planning sessions
i3 - Inspections
- Leverage the existing permit application framework to fast track development on the inspections module
- Target start date late February or early March
- Target finish date early June
i4 - Alterations
- Leverage the existing permit application framework to fast track development on the alterations module
- Target start date early July
- Target finish date early October
Summary
- HIC has been waiting to re-engage with HIOSH team
- Iteration 2 (i2) development is complete
- Finalize steps for Production deployment
- Iteration 3 nearly ready to start